8-12 T/H Alfalfa Pellet Production Line Project
Date: 12/21/2020 09:02:36 From: wood-pellet-plant.com Clicks:
An alfalfa pellet production line with an annual output of 20,000 tons uses a SZLH420 model pellet machine with an hourly output of 8-12 tons. This project is also an alfalfa pellet production line with an annual output of 8-12 tons. The raw material used in the production of this project is mainly alfalfa meal, with an annual consumption of 21,000 tons.
8-12 T/H Alfalfa Pellet Production Line Project
The project is located in the New Material Industrial Park of the Economic Development Zone of Guyuan City, Ningxia. Since the source of the raw materials for animal nutrition licking bricks in this project is unstable and has not been constructed in reality, this acceptance is only for the production line of alfalfa pellet feed with an annual output of 20,000 tons. If the construction unit constructs 50,000 tons of animal nutrition licking brick feed within the validity period of the environmental impact assessment (within five years of the environmental impact assessment approval) in the later period, it shall arrange the inspection and acceptance by itself. The project covers an area of 20026.10m2 (30 acres), and the main construction content includes office area, raw material warehouse, finished product warehouse, processing workshop, etc.
This project consists of main engineering, auxiliary engineering, public engineering, storage and transportation engineering and environmental protection engineering. See Table 2-1 for the specific project composition of the investigation and implementation.
Table 2-1 List of project composition
Engineering category | project | EIA construction scale and content | Actual construction scale and content | Changes | ||
structural work |
Alfalfa grass particles processing car between |
1F, arch-shaped color steel tile structure, building area of 600m 2 | 1F, arch-shaped color steel tile structure, building area is 600m 2 | No change in the same EIA |
||
Animal nutrition lick brick processing workshop |
1F, arch-shaped color steel tile structure, building area of 600m 2 | Due to the production of animal nutrition licking brick, animal camp construction and therefore not raise lick brick processing plant |
Reduced product variety |
|||
Alfalfa grass child Treasury |
1F, arch-shaped color steel tile structure, building area is 600m 2 |
1F, arch-shaped color steel tile structure, building area is 600m 2 |
No change in the same EIA | |||
Alfalfa Bale Storage Shed |
1F, arch-shaped color steel tile structure, construction area is 1000m 2 |
1F, arch-shaped color steel tile structure, construction area is 1000m 2 |
No change in the same EIA | |||
Finished product library | 1F, arch-shaped color steel tile structure, building area is 800m 2 |
1F, arch-shaped color steel tile structure, building area is 800m 2 |
No change in the same EIA | |||
Auxiliary engineering |
Office building |
6F, brick structure, covers an area of 1500m 2 , including marketing, office room, financial room, conference rooms, laboratories (laboratory project does not require water) |
After investigation, the actual construction of 1F, brick-concrete structure, covers an area of 800m 2 , including marketing department, office, financial room, meeting |
Reduced construction scale |
||
Wait | , Laboratory (laboratory project chamber need not water) etc. |
|||||
Restaurant and staff dormitory | 1F, brick-concrete structure, covering an area of 360m 2 , mainly providing staff meals and daily rest |
1F, brick structure, accounting for ground plot 360M 2 , mainly to provide staff meals and daily rest |
No change in the same EIA |
|||
Public works |
Water supply |
The water for the project is uniformly supplied by the water supply pipe network of the industrial park. The total water consumption is 2671.5m 3 /a, of which the raw material water consumption is 44m 3 /a, the domestic water consumption is 960m 3 /a, and the greening water consumption is 1667.5m 3 /a. |
It is supplied by the water supply pipe network of the industrial park. The total water consumption is 725m 3 /a, of which the domestic water consumption is 225m 3 /a and the greening water consumption is 500m 3 /a. |
Reduced water consumption and no production water |
||
drain |
The main drainage of the project is domestic sewage, with a discharge volume of 768m 3 /a. The domestic sewage is treated in the grease trap (effective volume 1.5m 3 ) and septic tank (effective volume 9m 3 ). In the near future, it will be collected in a tanker truck. Transport, enter the Guyuan City Sewage Treatment Plant for treatment, and enter the Park Sewage Treatment Plant for treatment after the sewage treatment plant of the New Material Industrial Park in the Economic Development Zone of Guyuan City, Ningxia is completed |
The drainage of the project is mainly domestic sewage with a discharge volume of 180m 3 /a. After the catering wastewater is treated in an oil-separated sedimentation tank (effective volume 1.5m 3 ), it is merged with domestic sewage treated in a septic tank (effective volume 9m 3 ). Sewage is cleaned out regularly and used for fertilization in the alfalfa test field. After the sewage treatment station of the New Material Industrial Park of Guyuan Economic Development Zone in Ningxia is completed and put into operation, it will enter the sewage treatment station of the park through the sewage pipe network for treatment |
At present, the sewage treatment plant in the New Material Industrial Park of Guyuan Economic Development Zone in Ningxia has not been completed and put into operation. There is no reception point for wastewater from this project. The domestic sewage of the project is refilled and then greened. After the sewage in the park is completed, the wastewater should pass through the established sewage pipe network in the park. Discharge into sewage treatment plant for treatment |
|||
powered by | Introduced by the city power grid, installed transformer , a corresponding supporting facilities |
Introduced by the city power grid, installed transformers, and supporting corresponding facilities |
No change in the same EIA | |||
Heating | The project mentioned by the winter heating heater for |
Project winter heating using electric heating device |
No change in the same EIA | |||
Environmental Engineering |
Waste gas treatment facilities |
The grinder is equipped with a bag filter (dust removal efficiency of 98%), the screening process has its own dust collector (the dust removal efficiency is 99%), the mixer has its own bag filter (the dust removal efficiency is 99%), and the oil fume purification facility (the purification efficiency is not Less than 80%) |
A small amount of high-end pet feed raw materials need to be crushed. The crusher comes with a bag filter; the pelletizer comes with a bag filter (dust removal efficiency of 99%), and oil fume purification facilities in the canteen (purification efficiency not less than 80%) |
No animal nutrition licking bricks are actually produced, and no mixers are installed |
||
Wastewater treatment facilities |
Oil trap (1.5m 3 ), septic tank (9m 3 ), reservoir (50m 3 ) |
Oil trap (1.5m 3 ), septic tank (9m 3 ) |
Due to the design phase campus water supply network is not completed, the construction unit plans to build reservoirs to store water for life, but the actual process of construction, the park has been built water supply network, and therefore does not build water storage tank |
|||
Noise control facilities |
Noise reduction, vibration reduction and noise prevention | The equipment is installed in the workshop, and the foundation is set with damping pads |
No change in the same EIA | |||
Solid Waste | Set up household garbage collection facilities | Set up household garbage collection facilities | No change in the same EIA | |||
Greening |
Green area is 3335m 2 , greening rate is 16.65% | The green area is 4000m 2 , the greening rate is 19.97% |
Green area increased |
The total design investment of this project is 50 million yuan, of which environmental protection investment is 870,000 yuan, accounting for 1.74% of the total investment; the actual total investment is 30 million yuan, of which the actual environmental protection investment is 400,000 yuan, accounting for 1.33% of the total investment. Used in waste gas treatment facilities, wastewater treatment facilities, vibration reduction and noise prevention, solid waste collection and treatment, and plant greening. Due to market reasons, no animal nutrition licks were actually produced, so the total investment and environmental protection investment decreased.
Table 2-2 List of main production equipment
Serial number | Equipment name | Specification model | unit | Design purchase quantity | Actual purchase quantity |
1 | Unloading pit, shed screen | / | A | 1 | 0 |
2 | Horizontal conveyor | TLSS30 | station | 1 | 0 |
3 | Hoist | TDTGK40/28 | station | 1 | 0 |
4 | Permanent magnet cylinder | TXCT25 | station | 1 | 0 |
5 | Round granulating bin | 10m 3 | station | 1 | 1 |
6 | Pan feeder | / | station | 1 | 1 |
7 | Granulator | SZLH420 | station | 1 | 1 |
8 | Feeder | GFZ.16 | station | 1 | 1 |
9 | Counter flow cooler | SKLN2.5 | station | 1 | 1 |
10 | Unloader | / | station | 1 | 1 |
11 | Hoist | TDTG36/18 | station | 1 | 1 |
12 | Finished product warehouse | 5m 3 | A | 5 | 0 |
13 | grinder | / | station | 1 | 0 |
14 | Belt conveyors | / | station | 1 | 1 |
15 | 4 Disc mower | MDM1700 | station | 2 | 1 |
16 | 2 Disc mower | MDM1300 | station | 1 | 1 |
17 | 7 Disc flattening mower | / | station | 2 | 1 |
18 | Baler | BC5070 | station | 3 | 1 |
19 | Round baler | MRB08970 | station | 1 | 1 |
20 | Silage coating machine | SWM0810 | station | 1 | 1 |
twenty one | Rotary machine | / | station | 1 | 1 |
twenty two | Hay rake | / | station | 2 | 1 |
twenty three | Manure spreader | / | station | 1 | 1 |
Labor Quota and Work System
The project has a labor quota of 15 people. The working system is 8 hours a day and 300 production days per year.
Brief Description of Production Process:
Hay Grass Alfalfa Pellet Machine
After the powdered feed enters the Hay Grass Alfalfa Pellet Machine, it is heated to 160°C, and the water in the alfalfa pellets is used to make alfalfa powder into alfalfa pellets, and then the hot pellets are passed through a cooler to reduce the temperature and humidity of the material and increase the hardness of the material , Reduce the powdering rate of materials. The cooling of this project adopts wind cooling. Through this section, pellet feed is produced. This granulator has its own screening process, grading and screening, and grading to obtain feed according to the product size requirements. The process of weighing, bagging and sewing the finished product by the automatic packaging equipment. After the packaging is completed, it is shipped to the finished product warehouse.
alfalfa pellets
Related Cases
South Africa 10 t/h Forage Grass Pellet Production Line
Saudi Arabia 5-6T/H & 10T/H Grass Alfalfa Pellet Production Line
USA 10-12T/H Forage Grass Pellet Production Line
China 3-4T/H Fresh grass Pellet Production Line
Indonesia 3-5T/H Alfalfa Straw Husk Pellet Line
The above is the article for you: 8-12 T/H Alfalfa Pellet Production Line Project. If you are interested in our products or project solutions, please contact us. We will give you the best product quality and the best price. Email: enquiry@pellet-richi.com
Related Product
Production Line Equipment
Related News
- >Good Price High Quality 20,000 Tons of Straw Chaff Husk Wood Pelle
- >Biomass Pellet Production Line Manufactures Straw Pellets, Wood Pe
- >100,000 Tons of Alfalfa Pellet Processing Production Line Construc
- >Newly Built 8 Forage Grass Pellet Production Lines in the Feed Fac
- >Investment Analysis of 5 Tons/hour Tofu Cat Litter Pellet Producti
- >10 Tons/hour Large-scale Organic Fertilizer Pellet Production Line
- >100,000 Tons of Alfalfa Product Processing Project and Pelleting P
- >Tofu Cat Litter and Plant Cat Litter Pellet Production Line Projec
- >10 T/h Pet Food Cat Litter Pellet Production Line Project
- >How to Make Hops Into Pellets? Need Hops Pellet Machine and Hops P
Here you can submit any questions and we will get back to you as soon as possible. We will not disclose the information you submit to anyone, please rest assured.
Copyright© 2020 Richi Machinery. All rights reserved. Site Map